RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 46.9 F058501C NW HOLY MOSES WASH - RATTLESNAKE WAS ZR1P PAVEMENT REHABILITATION PEDRAM SHAFIEIAN
602-712-8166
6/21/2024 Lee Makler
602-712-8579
Current Program Budget $42,077,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2023-05-17 A
Stage 2 - 30% 2023-10-05 A
Stage 3 - 60% 2024-01-18 A
Stage 4 - 95% 2024-05-11
EPG Clearance 2024-05-23
RW Clearance 2024-04-08 A
URR Clearance 2024-05-21
Stage 5 - 100% 2024-08-02
Advertise 2024-09-03
Bids Opening 2024-10-29