RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA APJ T037501C CL IRONWOOD DRIVE; BASELINE AVE - E YN1P PAVE SHOULDERS & RUMBLE STRIPS WESLEY SCATENA
602-712-8555
5/17/2024 Lee Makler
602-712-8579
Current Program Budget $1,736,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-15 A
Kickoff 2023-03-15 A
Stage 3 - 60% 2023-10-30 A
Stage 4 - 95% 2024-02-02 A
EPG Clearance 2024-01-26 A
RW Clearance 2024-01-31 A
URR Clearance 2024-03-21 A
Stage 5 - 100% 2024-03-29 A
Advertise 2024-05-17
Bids Opening 2024-06-14