RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T037201D CL MISSOURI AVE EASTWARD; 55TH AVE YH1P IMPROVE SIDEWALKS & ADA RAMPS CHRIS RODRIGUEZ
602-617-9560
5/27/2025 Lee Makler
602-712-8579
Current Program Budget $2,508,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-31 A
Stage 3 - 60% 2024-01-11 A
Stage 4 - 95% 2024-09-13 A
EPG Clearance 2024-06-17 A
RW Clearance 2025-03-28
URR Clearance 2024-12-03
Stage 5 - 100% 2025-03-28
Advertise 2025-05-27
Bids Opening 2025-07-19