Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2023-03-09 A |
Stage 3 - 60% | 2023-03-10 A |
Stage 4 - 95% | 2023-03-10 A |
EPG Clearance | 2023-04-18 A |
RW Clearance | 2023-05-31 A |
URR Clearance | 2023-04-04 A |
Advertise | 2023-10-12 A |
|
Arizona Department of Transportation |