Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-04-30
Kickoff 2022-05-09 A
Stage 3 - 60% 2023-03-20
Stage 4 - 95% 2023-05-01
EPG Clearance 2023-04-03 A
RW Clearance 2023-05-15
URR Clearance 2023-04-14
Stage 5 - 100% 2023-06-05
Advertise 2023-09-12
Bids Opening 2023-10-17
Award Date 2023-10-26