Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-04-30 |
Kickoff | 2022-05-09 A |
Stage 3 - 60% | 2023-03-20 |
Stage 4 - 95% | 2023-05-01 |
EPG Clearance | 2023-04-03 A |
RW Clearance | 2023-05-15 |
URR Clearance | 2023-04-14 |
Stage 5 - 100% | 2023-06-05 |
Advertise | 2023-09-12 |
Bids Opening | 2023-10-17 |
Award Date | 2023-10-26 |
|