RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA MES T035901D CL ELLIOT RD; EASTERN MARICOPA FLOOD XC1P DESIGN IMPROVEMENTS FOR ROADWAY WIDENING DANA CHERRY
602-712-7030
Design Lee Makler
602-712-8579
Current Program Budget $2,659,000 Program FY 22

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2024-11-16
EPG Clearance 2024-05-28
RW Clearance 2024-07-16
URR Clearance 2024-10-12
Stage 5 - 100% 2025-10-24
Advertise 2025-11-21




For Project Resource Office information or questions: PRO Mailbox