Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 SC NOG T035701C SC PATAGONIA HWY (SR82); MORLEY AVE WU1P MULTI USE PATH PEDRAM SHAFIEIAN
602-712-8166
6/21/2024 Lee Makler
602-712-8579
Current Program Budget $1,157,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2023-10-06 A
Stage 3 - 60% 2023-12-06 A
Stage 4 - 95% 2024-03-25 A
EPG Clearance 2024-04-27
RW Clearance 2024-05-11
URR Clearance 2024-05-11
Stage 5 - 100% 2024-05-21
Advertise 2024-06-21
Bids Opening 2024-07-20