Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-03-16 A |
Kickoff | 2023-03-16 A |
Stage 2 - 30% | 2023-03-16 A |
Stage 3 - 60% | 2023-09-11 A |
Stage 4 - 95% | 2023-10-11 A |
EPG Clearance | 2023-08-04 A |
RW Clearance | 2023-08-21 A |
URR Clearance | 2023-10-19 A |
Stage 5 - 100% | 2023-12-08 A |
Advertise | 2024-01-22 A |
Bids Opening | 2024-04-18 |
|
Arizona Department of Transportation |