RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T034301C CL 67 AVE & MONTEBELLO AVE WA1P PEDESTRIAN HYBRID BEACON ANGELA GALIETTI
602-712-7551
4/9/2024 Lee Makler
602-712-8579
Current Program Budget $273,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-10-27 A
Kickoff 2022-11-07 A
Stage 3 - 60% 2023-01-24 A
Stage 4 - 95% 2023-08-09 A
EPG Clearance 2023-03-30 A
RW Clearance 2023-06-08 A
URR Clearance 2023-08-31 A
Stage 5 - 100% 2024-02-23 A
Advertise 2024-04-09
Bids Opening 2024-06-13