Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GIL T033601C CL MEWS ROAD IMPROVEMENTS VL1P IMPROVE ROADWAY PATRICK O'LESKE
602-712-7629
3/14/2025 Lee Makler
602-712-8579
Current Program Budget $1,092,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-07-31 A
Kickoff 2023-08-07 A
Stage 2 - 30% 2023-08-07 A
Stage 3 - 60% 2023-10-30 A
Stage 4 - 95% 2024-03-04 A
EPG Clearance 2024-03-04 A
RW Clearance 2025-01-18
URR Clearance 2024-06-05 A
Stage 5 - 100% 2025-01-18
Advertise 2025-03-15
Bids Opening 2025-06-20