Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 YV 144.2 F081501C NW ASH FORK ATSF RR OP EB & ASH FORK VJ1Q DECK REHABILITATION CHRIS RODRIGUEZ
602-617-9560
11/4/2026 Lee Makler
602-712-8579
Current Program Budget $7,000,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-04-30 A
Stage 2 - 30% 2025-10-01
Stage 3 - 60% 2025-12-12
Stage 4 - 95% 2026-04-15
EPG Clearance 2026-02-20
RW Clearance 2026-04-15
URR Clearance 2026-05-08
Stage 5 - 100% 2026-08-07
Advertise 2026-11-04
Bids Opening 2027-02-20




For Project Resource Office information or questions: PRO Mailbox