Current Program Budget $3,830,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-07-24
Stage 2 - 30% 2025-08-09
Stage 3 - 60% 2025-08-12
Stage 4 - 95% 2025-09-02
EPG Clearance 2025-08-12
RW Clearance 2025-09-02
URR Clearance 2025-09-10
Stage 5 - 100% 2025-09-23
Advertise 2025-11-07
Bids Opening 2025-11-11