ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 MA 145.0 F079601C CL DECK PARK TUNNEL VB1Q DRAINAGE REPAIRS CHRIS MOORE
602-712-2132
Design Lee Makler
602-712-8579
Current Program Budget $346,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-06-06
Kickoff 2025-07-18
Stage 2 - 30% 2025-08-05
Stage 3 - 60% 2025-10-14
Stage 4 - 95% 2026-03-21
EPG Clearance 2025-11-13
RW Clearance 2026-01-27
URR Clearance 2026-03-31
Stage 5 - 100% 2026-04-11
Advertise 2026-05-28
Bids Opening 2026-05-30




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation