Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-11-20 A |
Kickoff | 2020-12-12 A |
Stage 2 - 30% | 2021-05-18 A |
Stage 3 - 60% | 2021-06-30 A |
Stage 4 - 95% | 2023-04-10 A |
EPG Clearance | 2022-12-19 A |
RW Clearance | 2023-05-03 A |
URR Clearance | 2023-05-26 A |
Stage 5 - 100% | 2023-05-24 A |
Advertise | 2024-01-25 A |
Bids Opening | 2024-04-19 A |
|