Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-08-02 A |
Kickoff | 2025-08-26 |
Stage 2 - 30% | 2025-09-02 |
Stage 3 - 60% | 2026-02-18 |
Stage 4 - 95% | 2026-05-13 |
EPG Clearance | 2025-10-11 |
RW Clearance | 2026-05-20 |
URR Clearance | 2026-05-16 |
Stage 5 - 100% | 2026-07-27 |
Advertise | 2026-09-22 |
Bids Opening | 2026-11-21 |
|
Arizona Department of Transportation |