RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA MMA T063601X CL MCDOT INTERCONNECTION UPGRADES 20 UK1Q PROCURE COMMUNICATION DEVICES DANA CHERRY
602-712-7030
5/1/2025 Lee Makler
602-712-8579
Current Program Budget $492,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-12-30 A
EPG Clearance 2025-03-10 A
RW Clearance 2025-03-14 A
URR Clearance 2025-04-16
Stage 5 - 100% 2025-05-02
Advertise 2025-05-06