Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-05-25 A |
Kickoff | 2021-07-15 A |
Stage 3 - 60% | 2021-10-22 A |
Stage 4 - 95% | 2022-01-14 A |
EPG Clearance | 2022-01-28 A |
RW Clearance | 2022-02-25 A |
URR Clearance | 2022-03-02 A |
Stage 5 - 100% | 2022-03-11 A |
Advertise | 2022-05-27 A |
Bids Opening | 2022-06-17 A |
|