Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-08-11 A |
Kickoff | 2023-08-16 A |
Stage 3 - 60% | 2023-10-12 A |
Stage 4 - 95% | 2023-12-15 A |
EPG Clearance | 2023-12-15 A |
RW Clearance | 2024-01-05 A |
URR Clearance | 2024-02-08 A |
Stage 5 - 100% | 2024-02-15 A |
Advertise | 2024-02-26 A |
Bids Opening | 2024-04-20 |
|