RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
303L MA 118.0 F047201C CL SR303L & US60 TI UG1P NEAR TERM IMPROVEMENTS TRICIA BROWN
602-712-7046
4/25/2024 Lee Makler
602-712-8579
Current Program Budget $4,390,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-11 A
Kickoff 2023-08-16 A
Stage 3 - 60% 2023-10-12 A
Stage 4 - 95% 2023-12-15 A
EPG Clearance 2023-12-15 A
RW Clearance 2024-01-05 A
URR Clearance 2024-02-08 A
Stage 5 - 100% 2024-02-15 A
Advertise 2024-02-26 A
Bids Opening 2024-04-20