ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2021-11-09 A
Kickoff 2021-11-30 A
Stage 3 - 60% 2022-06-24 A
Stage 4 - 95% 2022-10-07 A
EPG Clearance 2022-06-27 A
RW Clearance 2022-07-08 A
URR Clearance 2022-10-20 A
Stage 5 - 100% 2023-02-01 A
Advertise 2023-02-10 A
Bids Opening 2023-04-21 A




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation