Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-12-06 A |
Kickoff | 2021-12-06 A |
Stage 3 - 60% | 2022-04-15 A |
Stage 4 - 95% | 2022-08-08 A |
EPG Clearance | 2022-05-05 A |
RW Clearance | 2022-05-27 A |
URR Clearance | 2022-08-11 A |
Stage 5 - 100% | 2022-10-28 A |
Advertise | 2022-12-15 A |
Bids Opening | 2023-03-03 A |
|
Arizona Department of Transportation |