Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2021-11-12 A
Kickoff 2021-11-22 A
Stage 4 - 95% 2022-02-25 A
EPG Clearance 2022-04-28 A
RW Clearance 2022-03-21 A
URR Clearance 2022-03-29 A
Stage 5 - 100% 2022-04-29 A
Advertise 2022-06-08 A
Bids Opening 2022-08-19 A