RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 235.0 F077501D NC METEOR CRATER REST AREA TL1Q TRUCK PARKING EXPANSION RAYMUNDO BACA
602-679-0072
Design Lee Makler
602-712-8579
Current Program Budget $830,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 3 - 60% 2026-04-03
EPG Clearance 2025-09-05
RW Clearance 2026-03-04
URR Clearance 2025-12-10
Stage 5 - 100% 2026-03-04
Advertise 2026-05-29