Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-11-12 A |
Kickoff | 2021-11-22 A |
Stage 4 - 95% | 2022-02-18 A |
EPG Clearance | 2022-03-31 A |
RW Clearance | 2022-03-17 A |
URR Clearance | 2022-03-16 A |
Stage 5 - 100% | 2022-04-29 A |
Advertise | 2022-06-06 A |
Bids Opening | 2022-07-15 A |
|
Arizona Department of Transportation |