ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
77 NA 388.0 F069701C NE LITTLE COLORADO RIVER BRIDGE TH1O BRIDGE REHABILITATION THOMAS O'REILLY
602-712-2587
7/25/2025 Lee Makler
602-712-8579
Current Program Budget $3,500,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-10-27 A
Kickoff 2023-10-25 A
Stage 2 - 30% 2024-06-22
Stage 3 - 60% 2024-09-21
Stage 4 - 95% 2024-12-14
EPG Clearance 2024-11-23
RW Clearance 2025-02-01
URR Clearance 2025-02-08
Stage 5 - 100% 2025-03-22
Advertise 2025-07-26
Bids Opening 2025-09-20




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation