RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 CH BIS T062101C SE SR 80; QUEEN MINE TOUR - OLD BISB SX1Q CONSTRUCT SHARED USE PATH ARASH GHAZANFARI
602-712-8336
5/29/2026 Lee Makler
602-712-8579
Current Program Budget $3,635,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-04-09 A
Stage 2 - 30% 2025-08-01
Stage 3 - 60% 2025-10-31
Stage 4 - 95% 2026-02-19
EPG Clearance 2026-01-24
RW Clearance 2026-04-18
URR Clearance 2026-04-18
Stage 5 - 100% 2026-04-25
Advertise 2026-05-30
Bids Opening 2026-07-30