RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 YV SED T062001C NC SHELBY DR BUSINESS DEVELPMENT PHA SV1Q SHARED USE PATH JUDAH CAIN
602-712-4493
8/1/2025 Lee Makler
602-712-8579
Current Program Budget $1,500,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-03-20
Kickoff 2025-03-04
Stage 2 - 30% 2025-03-20
Stage 3 - 60% 2025-03-21
Stage 4 - 95% 2025-04-11
EPG Clearance 2025-04-04
RW Clearance 2025-04-11
URR Clearance 2025-04-19
Stage 5 - 100% 2025-05-02
Advertise 2025-06-18
Bids Opening 2025-06-20