ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 YV 298.9 F031401C NC SR 179 TI OP SB SQ1O BRIDGE REHABILITATION SANDY THOMS
602-712-7607
7/11/2025 Jeff Ross
602-712-8477
Current Program Budget $2,369,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-03-19 A
Kickoff 2024-04-22 A
Stage 2 - 30% 2024-09-06 A
Stage 3 - 60% 2024-11-16
Stage 4 - 95% 2025-02-08
EPG Clearance 2025-01-18
RW Clearance 2025-03-29
URR Clearance 2025-03-29
Stage 5 - 100% 2025-03-29
Advertise 2025-07-12
Bids Opening 2025-08-23




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation