RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
17 YV 298.9 F031401D NC SR 179 TI OP SB SQ1O BRIDGE REHABILITATION SANDY THOMS
602-712-7607
TBD Jeff Ross
602-712-8477
Current Program Budget $2,000,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-04-02
Kickoff 2024-04-16
Stage 2 - 30% 2024-07-30
Stage 3 - 60% 2024-11-05
Stage 4 - 95% 2025-01-21
EPG Clearance 2024-12-07
RW Clearance 2025-02-18
URR Clearance 2025-02-25
Stage 5 - 100% 2025-04-08
Advertise 2025-07-19
Bids Opening 2025-08-30