Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-04-27 A |
Kickoff | 2022-05-11 A |
Stage 1 - 15% | 2021-07-01 A |
Stage 3 - 60% | 2022-09-21 A |
Stage 4 - 95% | 2023-05-09 A |
EPG Clearance | 2022-11-15 A |
RW Clearance | 2024-01-22 A |
URR Clearance | 2024-04-08 A |
Stage 5 - 100% | 2024-04-27 |
Advertise | 2024-06-01 |
Bids Opening | 2024-07-20 |
|