ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2022-05-10 A
Kickoff 2022-05-26 A
Stage 3 - 60% 2023-03-16 A
Stage 4 - 95% 2023-06-30 A
EPG Clearance 2023-09-07 A
RW Clearance 2023-09-07 A
URR Clearance 2023-07-26 A
Stage 5 - 100% 2023-09-01 A
Advertise 2023-11-02 A
Bids Opening 2024-01-26 A
Award Date 2024-02-16 A




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation