Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-05-10 A |
Kickoff | 2022-05-26 A |
Stage 3 - 60% | 2023-03-16 A |
Stage 4 - 95% | 2023-06-30 A |
EPG Clearance | 2023-09-07 A |
RW Clearance | 2023-09-07 A |
URR Clearance | 2023-07-26 A |
Stage 5 - 100% | 2023-09-01 A |
Advertise | 2023-11-02 A |
Bids Opening | 2024-01-26 A |
Award Date | 2024-02-16 A |
|