RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 AP 340.0 F082301C SANDERS PORT OF ENTRY SA1Q REPLACE SCALE & CONSTRUCT INSPECTION PIT CHRIS MOORE
602-712-2132
TBD Lee Makler
602-712-8579
Current Program Budget $4,800,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-07-10
Kickoff 2025-10-01
Stage 2 - 30% 2025-12-20
Stage 3 - 60% 2026-05-23
Stage 4 - 95% 2026-10-17
EPG Clearance 2026-07-08
RW Clearance 2026-10-19
URR Clearance 2026-10-27
Stage 5 - 100% 2027-02-20
Advertise 2027-04-08
Bids Opening 2027-04-10