Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 4 - 95% | 2025-07-05 |
EPG Clearance | 2025-02-17 |
RW Clearance | 2025-07-07 |
URR Clearance | 2025-07-10 |
Stage 5 - 100% | 2025-10-25 |
Advertise | 2025-12-11 |
Bids Opening | 2026-01-28 |
|