Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-02-25 A |
Kickoff | 2022-02-25 A |
Stage 2 - 30% | 2022-03-09 A |
Stage 4 - 95% | 2022-07-02 |
EPG Clearance | 2022-08-20 |
RW Clearance | 2022-08-13 |
URR Clearance | 2022-08-18 |
Stage 5 - 100% | 2022-09-13 |
Advertise | 2022-10-19 |
Bids Opening | 2022-12-17 |
|