RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PN CLG T059501C SC CASA GRANDE CANAL EXTENSION BRIDG QO1Q REPLACE BRIDGE VIVIAN LI
602-712-8708
TBD Lee Makler
602-712-8579
Current Program Budget $2,136,000 Program FY 28

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-06-19 A
Kickoff 2025-11-01
Stage 2 - 30% 2025-11-19
Stage 3 - 60% 2026-02-14
Stage 4 - 95% 2026-05-21
EPG Clearance 2026-05-01
RW Clearance 2026-07-25
URR Clearance 2026-05-29
Stage 5 - 100% 2026-07-25
Advertise 2026-09-10
Bids Opening 2026-09-12