RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 PN 173.7 F073401C CL GILA RIVER BRIDGE - GAS LINE RD QM1Q WIDEN ROADWAY TRENT KELSO
602-712-6685
5/15/2026 Lee Makler
602-712-8579
Current Program Budget $137,848,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-02-06 A
Stage 3 - 60% 2025-08-01
Stage 4 - 95% 2026-01-13
EPG Clearance 2026-02-20
RW Clearance 2026-02-20
URR Clearance 2026-03-18
Stage 5 - 100% 2026-03-18
Advertise 2026-05-16
Bids Opening 2026-07-23




For Project Resource Office information or questions: PRO Mailbox