Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 4 - 95% | 2025-05-10 |
EPG Clearance | 2025-05-10 |
RW Clearance | 2025-05-12 |
URR Clearance | 2025-04-24 A |
Stage 5 - 100% | 2025-05-31 |
Advertise | 2025-08-02 |
Bids Opening | 2025-08-06 |
|