RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 CH DGS T058101C SE CHINO RD PHASE II; 9TH ST - SR 90 QA1Q ROAD REALIGNMENT CHINWE IWUCHUKWU
626-222-7982
8/1/2025 Lee Makler
602-712-8579
Current Program Budget $4,807,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2025-05-10
EPG Clearance 2025-05-10
RW Clearance 2025-05-12
URR Clearance 2025-04-24 A
Stage 5 - 100% 2025-05-31
Advertise 2025-08-02
Bids Opening 2025-08-06