Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2024-09-26 A |
Stage 3 - 60% | 2025-01-11 |
Stage 4 - 95% | 2025-03-29 |
EPG Clearance | 2025-02-01 |
RW Clearance | 2025-03-22 |
URR Clearance | 2025-03-29 |
Stage 5 - 100% | 2025-06-28 |
Advertise | 2025-07-26 |
Bids Opening | 2025-10-04 |
|