RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T031101C CL PALMAIRE AVE; 46TH AVE; BETHANY H PT1P CENTRAL CORE SIDEWALK CLOSURES RASHIDUL HAQUE
602-712-7352
11/5/2024 Jeff Ross
602-712-8477
Current Program Budget $2,770,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2021-10-21 A
Kickoff 2021-11-02 A
Stage 2 - 30% 2022-04-15 A
Stage 3 - 60% 2022-07-08 A
Stage 4 - 95% 2023-06-27 A
EPG Clearance 2022-10-21 A
RW Clearance 2023-06-27 A
URR Clearance 2023-11-29 A
Stage 5 - 100% 2024-02-28 A
Advertise 2024-11-05 A
Bids Opening 2024-11-16