RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 50.0 F074301D CL MCCLINTOCK DR - 48TH ST PQ1Q CONVERT HPS TO LED LIGHTING JEFFREY DAVIDSON
602-712-8534
TBD Lee Makler
602-712-8579
Current Program Budget $260,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-12-07
Kickoff 2024-09-18
Stage 2 - 30% 2024-09-18
Stage 3 - 60% 2024-09-18
Stage 4 - 95% 2024-10-08
EPG Clearance 2024-09-17
RW Clearance 2024-09-17
URR Clearance 2024-09-25
Stage 5 - 100% 2024-10-08
Advertise 2024-11-01
Bids Opening 2024-09-19