ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 50.0 F074301D CL MCCLINTOCK DR - 48TH ST PQ1Q CONVERT HPS TO LED LIGHTING JEFFREY DAVIDSON
602-712-8534
Design Lee Makler
602-712-8579
Current Program Budget $260,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2025-02-18 A
Stage 4 - 95% 2025-03-03 A
EPG Clearance 2025-03-21 A
RW Clearance 2025-04-07 A
URR Clearance 2025-03-12 A
Stage 5 - 100% 2025-04-26
Advertise 2025-08-30
Bids Opening 2025-07-19




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation