Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-02-07 A |
Kickoff | 2022-02-15 A |
Stage 3 - 60% | 2022-08-08 A |
Stage 4 - 95% | 2023-08-11 A |
EPG Clearance | 2022-09-12 A |
RW Clearance | 2023-11-13 A |
URR Clearance | 2024-03-30 |
Stage 5 - 100% | 2024-04-19 |
Advertise | 2024-05-18 |
Bids Opening | 2024-07-27 |
|