RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 32.0 F074601C CL GUADALUPE - SANTAN VILLAGE PARKWA PC1Q CONVERT HPS TO LED LIGHTING CONNIE CORVALAN
602-712-3062
1/31/2025 Lee Makler
602-712-8579
Current Program Budget $800,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-08-21 A
Kickoff 2024-08-23 A
Stage 3 - 60% 2024-12-03
EPG Clearance 2025-01-04
RW Clearance 2025-01-18
URR Clearance 2025-01-18
Stage 5 - 100% 2025-01-14
Advertise 2025-02-01
Bids Opening 2025-03-15