Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 32.0 F074601D CL GUADALUPE - SANTAN VILLAGE PARKWA PC1Q CONVERT HPS TO LED LIGHTING CONNIE CORVALAN
602-712-3062
Design Lee Makler
602-712-8579
Current Program Budget $260,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-05-28
Kickoff 2024-06-11
Stage 3 - 60% 2024-08-13
Stage 4 - 95% 2024-11-02
EPG Clearance 2024-07-23
RW Clearance 2024-11-30
URR Clearance 2024-12-07
Stage 5 - 100% 2024-12-07
Advertise 2025-01-09
Bids Opening 2025-02-20




For Project Resource Office information or questions: PRO Mailbox