Current Program Budget $1,342,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-03-05
Kickoff 2025-02-15
Stage 2 - 30% 2025-03-05
Stage 3 - 60% 2025-03-06
Stage 4 - 95% 2025-03-27
EPG Clearance 2025-03-06
RW Clearance 2025-03-27
URR Clearance 2025-04-04
Stage 5 - 100% 2025-04-17
Advertise 2025-06-03
Bids Opening 2025-06-05