Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-09-17 A |
Kickoff | 2024-09-19 A |
Stage 4 - 95% | 2024-10-25 A |
EPG Clearance | 2024-12-17 |
RW Clearance | 2024-11-14 A |
URR Clearance | 2024-12-17 |
Advertise | 2025-02-22 |
Bids Opening | 2025-04-19 |
|