RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 YU YUM T055601D SW 32ND STREET, AVENUE 3E - AVENUE 7 OD1Q CONSTRUCT SHARED USE PATHWAY FRANK FRY
602-228-5378
4/24/2026 Lee Makler
602-712-8579
Current Program Budget $334,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 2 - 30% 2025-06-11
Stage 3 - 60% 2025-10-15
Stage 4 - 95% 2026-01-14
EPG Clearance 2025-12-19
RW Clearance 2026-02-04
URR Clearance 2026-02-18
Stage 5 - 100% 2026-03-25
Advertise 2026-04-24