Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-01-05
Kickoff 2025-01-28
Stage 2 - 30% 2025-03-22
Stage 3 - 60% 2025-03-25
Stage 4 - 95% 2025-07-12
EPG Clearance 2025-07-12
RW Clearance 2025-07-14
URR Clearance 2025-07-22
Stage 5 - 100% 2025-08-16
Advertise 2025-10-02
Bids Opening 2025-10-04