Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-06-04 A |
Kickoff | 2024-07-16 A |
Stage 3 - 60% | 2024-11-12 A |
Stage 4 - 95% | 2025-02-27 |
EPG Clearance | 2025-02-12 |
RW Clearance | 2025-04-23 |
URR Clearance | 2025-05-08 |
Stage 5 - 100% | 2025-05-01 |
Advertise | 2025-05-29 |
Bids Opening | 2025-07-10 |
|