RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 NA PLS T060501C NE E WOODLAND LAKE RD; S WOODLAND LN NS1Q CONSTRUCT ROADWAY IMPROVEMENTS CHRIS RODRIGUEZ
602-617-9560
6/30/2026 Lee Makler
602-712-8579
Current Program Budget $210,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2025-04-18 A
Kickoff 2025-05-21 A
Stage 2 - 30% 2025-06-12 A
Stage 3 - 60% 2025-09-20
Stage 4 - 95% 2026-01-31
EPG Clearance 2026-01-20
RW Clearance 2026-03-13
URR Clearance 2026-02-10
Stage 5 - 100% 2026-05-09
Advertise 2026-06-30
Bids Opening 2026-08-25