RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 GH GGH T053501D SE GILA RIVER LINEAR PARK & TRAIL NM1Q LINEAR PARK ALONG GILA RIVER TRICIA BROWN
602-712-7046
Design Lee Makler
602-712-8579
Current Program Budget $499,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-01-23
Kickoff 2024-01-23
Stage 2 - 30% 2024-02-07
Stage 3 - 60% 2024-03-02
Stage 4 - 95% 2024-03-16
EPG Clearance 2024-03-16
RW Clearance 2024-01-27
URR Clearance 2024-01-30
Stage 5 - 100% 2024-02-10
Advertise 2024-01-23
Bids Opening 2024-01-23