Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2024-10-24 A |
Stage 2 - 30% | 2024-10-24 A |
Stage 3 - 60% | 2025-02-01 |
Stage 4 - 95% | 2025-05-17 |
EPG Clearance | 2025-04-26 |
RW Clearance | 2025-06-07 |
URR Clearance | 2025-06-07 |
Stage 5 - 100% | 2025-06-07 |
Advertise | 2025-08-19 |
Bids Opening | 2025-08-21 |
|