Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-04-08 A |
Kickoff | 2021-04-06 A |
Stage 2 - 30% | 2021-10-25 A |
Stage 3 - 60% | 2022-05-11 A |
Stage 4 - 95% | 2023-03-10 A |
EPG Clearance | 2022-05-31 A |
RW Clearance | 2023-08-11 A |
URR Clearance | 2023-08-03 A |
Stage 5 - 100% | 2023-08-31 A |
Advertise | 2023-09-07 A |
Bids Opening | 2024-01-12 A |
|