RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
999 SW 0.0 F072501C SW I-8 AND SR 85, AND I-10 AND RIGG NB1Q INSTALL DYNAMIC MESSAGE SIGNS PEDRAM SHAFIEIAN
602-712-8166
8/21/2025 Lee Makler
602-712-8579
Current Program Budget $1,500,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-12-10 A
Kickoff 2024-12-10 A
Stage 3 - 60% 2024-12-18 A
Stage 4 - 95% 2025-05-03
EPG Clearance 2025-07-19
RW Clearance 2025-03-25 A
URR Clearance 2025-06-20
Stage 5 - 100% 2025-07-26
Advertise 2025-08-21
Bids Opening 2025-10-18